Below are two case studies showing the critical role Canbrella plays in your project.
Case Study Number One
David & Julie signed an agreement with Empire Kitchens. The agreement was in the amount of $29,900 for new kitchen cabinets. $15,000 deposit and balance on delivery of $14,900.
Facts are:
1. The supplier went past delivery date
2. Interior of kitchen cabinets did not match
3. Cabinet doors did not match
4. Installation took weeks after delivery
5. Wine rack collapsed
6. Moldings not matching and crooked
Outcome
1. Legal costs were incurred
2. Months later and still not completed
3. Company has changed owners and name
4. Other companies have said they should take the loss and start over.
5. Emotional conflicts by homeowner
Presently, still proceeding with court action. Kitchen cabinets still not finished.
Canbrella’s Role
1. Canbrella would have maintained a start date and finish date
2. Would have maintained monetary control until project was finished to the satisfaction of Canbrella and principle
3. Minimized cost to client by ensuring completion of contracted work
Case Study Number Two
Jass went and purchased an industrial property at 7 Research Rd, Brampton. All other businesses on this court were automotive. Thinking that he could have the same type of business, he purchased it. Not knowing the zoning had changed and he was not able to grandfather his proposed automotive business.
Canbrella’s Role
1. Due diligence on the properties overall results
2. Understanding of zoning and construction regulations
3. Protect the buyer, providing less overall cost